Sprint 2 Planning

05-03-2012

I’ve had to take a week break from project work to complete other assignments.
Planning for Sprint 2. The plan is:

Collision Detection. Get the collision forces and vectors calculated correctly.
Gravity: turn down the gravity to a slightly more realistic scale. The idea being that the gravitations might be less dramatic but more realistic and more importantly more manageable while ‘playing’ the game.

Triple all my time estimations.

While planning Sprint 2 I estimated that I’d need 13 hours to complete all the tasks I wanted to complete on this sprint. Looking at my current workload I couldn’t see how I could schedule in that many hours. So I had to push from of the tasks to a later sprint.